List of Construction Projects on Campus
| Project | Estimated Cost | Start Date | Project Progress |
|---|---|---|---|
|
New University Center
|
$80M
|
07/2022
|
In Construction
|
|
Chick-fil-A Fitout
|
$1.8M
|
01/2025
|
In Construction
|
|
New Tennis Court Complex
|
$1.4M
|
03/2025
|
Completed
|
|
Misc. Concrete Repairs
|
$44K
|
05/2025
|
On hold until Spring 2026
|
|
Minsi Masonry Repairs
|
$1.2M
|
05/2025
|
On hold until May 2026
|
|
Koehler Fieldhouse Storefront Replacement
|
$160K
|
03/2026
|
Bid Awarded
|
|
Minsi Roof Replacement
|
$350K
|
05/2026
|
Waiting on bid
|
|
Mattioli Roof Replacement
|
$450K
|
05/2026
|
Waiting on bid
|